The drainage infrastructure on the Bathgate to Edinburgh railway line will be improved by an £800,000 investment from Network Rail.

Engineers will install around 800 metres of new larger drainage pipes near Bathgate station. It is hoped this will reduce the risk of flooding on the route. Teams will also inspect and clear existing drainage to ensure the drainage works effectively.

This work will affect services on 15, 22 and 29 March when trains will run from Helensburgh to Bathgate. Replacement buses will carry passengers between Bathgate and Haymarket which will call at all intermediate stations.

Eddie McLoone, project manager at Network Rail Scotland said: “It’s been 15 years since the Airdrie-Bathgate line was reopened, and we’re continuing to invest in the parts of the infrastructure that will keep this route resilient for many more years to come.

“Drainage might not be the most visible part of the network, but it plays a vital role in keeping trains moving reliably. By strengthening this section of the line now, we’re helping protect services from the disruption that heavy rainfall can bring.

“We know there’s never a good time to close any part of the railway, and we appreciate everyone’s patience during the three Sundays in March while we carry out these improvements.”

Mark Ilderton, ScotRail service delivery director, said: “The drainage improvements being delivered by Network Rail are an important investment in the long-term resilience of the route between Bathgate and Edinburgh.

“While there will be some temporary changes to services on the three Sundays in March, we’ll have a robust rail replacement plan in place to allow customers to continue to travel with confidence.

“We’re working closely with Network Rail to ensure clear information is available for customers to plan their journeys in advance.

“I’d encourage anyone planning to travel on 15, 22, or 29 March to check their journey before setting off and allow some extra time for travel where needed.”

Maintenance teams will also clear overgrown vegetation and inspect structures along the route to help keep services running safely and reliably – maximising the time the railway is closed and reducing the need for future disruption for passengers.  

Passengers are encouraged to check with their train operator or nationalrail.co.uk  before travelling and follow @NetworkRailSCOT on X for the latest updates.