Roads to be resurfaced from end of May

The council has announced plans to resurface certain streets in the city centre and surrounding the tram route to Newhaven with works beginning on 27 May.

The work will start in Abercromby Place and will include resurfacing the carriageway, pedestrian access and public realm improvements as well as traffic signal upgrades. Traffic lights will be installed at the junction at Easter Road/Lochend Road and Duke Street.

This is part of the council’s plan to spend £125m on city roads and footpaths over five years and has been brought forward from next year.

Various sections of Easter Road will be included in the planned resurfacing works

All local residents and businesses in the area should receive information about the projects ahead of the work beginning. With thanks to Leith Links Community Council who put all of this in a neat table.

Street Month Treatment Proposed Traffic Mgmt
Abercromby Place May Fully Resurfaced Road closure.
Local diversion
North Leith Sands May Fully Resurfaced Road closure.
Local diversion
Albany Street June Fully Resurfaced Road closure.
Local diversion
Lindsay Road June Fully Resurfaced from North Leith Sands to Portland Street One-way closure.
Local diversion
Broughton Street June Full Resurfaced Northbound road closure
Ocean Drive June Fully Resurface both northbound lanes from Lindsay Road to roundabout, and southbound bus stop at Holiday Inn Road closure.
Local diversion
East London Street June Fully resurface from roundabout to Cochran Terrace Lane closures
Annandale Street June Fully resurface from Haddington Place to roundabout and from roundabout to Hopetoun Street Road closure in 3 phases.
Local diversion
Great Junction Street June Fully resurface from Cables Wynd to Henderson Street Lane closures or Eastbound closure with local diversion
Dalmeny Street July Overlay setts in centre of carriageway (retain setts in parking areas) Road closure. Local diversion
Hopetoun Street July Various sections resurfaced Full road closure. Local diversion
Gordon Street July Fully resurfaced and overlay setts on Manderston Street Road closure. Local diversion
McDonald Road July Resurface eastbound bus stop at Papermill Wynd Lane closure or southbound closure with local diversion
Broughton Road July Fully resurfaced from Broughton Primary to Bonnington Road Road closure in 2 phases.
Local diversion
Links Place July Fully resurfaced Road closure.
Local diversion
Duncan Place July Fully resurfaced Road closure.
Local diversion
Bonnington Road July Fully resurfaced from Broughton Road to Corunna Place Road closure in 3 phases.
Local diversion
Academy Street July Overlay setts in running lanes (retain setts in parking areas) Road closure.
Local diversion
Newhaven Road August Fully resurfaced from Pilrig Street to Pitt Street Road closure in 2 phases.
Local diversion
East Hermitage / Restalrig Rd Junction August Fully resurface Junction area Temporary Traffic Lights and closure of Links Gardens. Local Diversion
Duke Street / Easter Road Junction August Fully resurface roundabout and approaches Temporary traffic lights
Pilrig Street August Fully resurfaced from Spey Street to Newhaven Road Road closure in 2 phases.
Local diversion
Easter Road August Various sections resurfaced Various lane closures and temporary traffic lights.
Possible road closure required at Albion Road with local diversion